MECHANICAL INSTALLATION

The mechanical installation includes installing the posts and mounting the softball timer to the posts.

Post Installation

The softball timer mounts on two posts. Typically installers will use steel pipes or I-beams. In order to reduce the glare from the sun on the front of the softball timer, position the posts so that the front of the softball timer is angled away from the afternoon sun, if possible. The mounting hardware will accommodate posts up to 4.5 inches outer diameter. Sink the posts in reinforced concrete footings. Figure 1 shows the spacing of the posts for a 1064 softball timer. The specifications for the posts and concrete footings are dependent upon the expected local wind and soil conditions, the height of the softball timer from the ground, and the local building codes. Electro-Mech Scoreboard Company assumes no responsibility for installations performed by others.

 

 

Figure 1  1064 Post Spacing
Figure 1 1064 Post Spacing Mounting The Softball Timer

The softball timer is attached to the posts at four points. Figure 2 shows the location of the mounting points on the rear of the softball timer.

 

Figure 2  Mounting Points
Figure 2 Mounting Points

 

Previous Chapter Back to Scoreboard 1064 Manual Next Chapter